MV Chengtu

Ship hold/bulkhead repairs

> Crop out and repair severely indented starboard aft end wall - 1.2m x 9.6m section
> Crop out damaged combings and hatches x2 from deck, manufacture and replace with new
> Crop out complete door assembly to aft central bulk head
> Manufacture new door plus frame and fit into place
> Crop out 20x channel shaped sections 1.8m x 2m high, manufacture new and replace
> Crop out 3.3m x 8m section, repair frames and replace
> Repair Co2 piping